This analysis tracks Dubai Creek Harbour supply and the apartment market in Emaar's waterfront community from 2023 to the third quarter of 2026. We look at resale prices, rents, yields, new supply and the projects that have not yet been built.

For investors, the key question is timing. Prices rose by about a fifth between 2023 and 2025, but the third quarter of 2026 brought falls in prices, transaction numbers and rents. Much of what is planned for the area, including the metro, the mall and the tower, has not been completed yet.

For the full analysis of resale prices, yields and liquidity in the area, see our Dubai Creek Harbour case study. Here we focus on what is still to be built and how the new supply affects investors.

Background: Emaar's Waterfront Community

Dubai Creek Harbour sits on the banks of Dubai Creek, next to the Ras Al Khor Wildlife Sanctuary. It began as a joint venture between Emaar and Dubai Holding, and in 2022 came under Emaar's full ownership, according to Metropolitan. It is a freehold area where foreigners can buy property outright. Most homes are apartments, though some newer projects also include townhouses.

According to Emaar, about 70% of the master plan area has not yet been developed, and on completion the community is expected to have 75,500 homes and more than 200,000 residents, as published by Arabian Business in content sponsored by Emaar. In a community of this size, no single launch price represents the whole area. Our Creek Gate case study follows one of the first towers in the area from launch to the resale market.

For the full picture, read our Dubai Creek Harbour area guide and the Emaar developer profile. Our guide to Emaar for Israeli investors gives a deeper introduction to the developer.

Prices: Gains to 2025, Weakness in Q3 2026

All figures in this section are averages for resale apartment transactions only, from Metropolitan reports. Direct developer sales are not included.

PeriodAverage resale price per sq ft, AEDAverage price per sqm, AEDChange
20231,922About 20,690Not stated
20242,189About 23,560Up 13.9% on 2023
20252,332About 25,100Up 6.5% on 2024
H1 20262,399About 25,820Up 5.3% on H1 2025
Q3 20262,300About 24,760Down 2.7% on Q3 2025

Source: Metropolitan reports for 2024, 2025, H1 2026 and Q3 2026, based on Property Monitor data. Prices per sqm were calculated from prices per sq ft, at 10.764 sq ft per sqm.

The average rose about 21% between 2023 and 2025. The peak in the data series came in the first quarter of 2026, at AED 2,446 per sq ft. By the third quarter, the average was about 6% below that peak.

Averages also shift with the mix of apartments sold, so it is worth looking at the split by number of bedrooms. In the third quarter, average prices fell for one- and two-bedroom apartments, while three-bedroom apartments saw a slight rise.

Apartment type, Q3 2026Average resale priceAnnual price changeAverage annual rentAnnual rent change
One bedroomAED 1,736,320Down 1%AED 92,978Down 5.1%
Two bedroomsAED 2,698,647Down 3.1%AED 139,611Down 7%
Three bedroomsAED 4,222,476Up 1.9%AED 216,047Down 5.3%

Source: Metropolitan Q3 2026 report. Changes are compared with Q3 2025. Rent data includes short-term and long-term contracts.

Comparison with Other Areas

The first table compares resale apartment prices only, for the same quarter and from the same source.

Area, Q3 2026Resale price per sq ft, AEDAnnual price changeResale transactionsAnnual change in transactions
Downtown Dubai2,730Down 0.1%353Down 32.9%
Dubai Creek Harbour2,300Down 2.7%294Down 28.1%
Dubai Hills Estate2,247Down 6.1%352Up 28.9%
Business Bay1,961Down 2.9%669Down 18.5%
Dubai Marina1,857Down 4.2%375Down 33.2%
Jumeirah Village Circle (JVC)1,225Down 5.9%956Down 27.5%

Source: Metropolitan resale reports for Q3 2026.

On the resale market, Dubai Creek Harbour is about 16% cheaper than Downtown Dubai and about 17% more expensive than Business Bay.

For more on the other areas in the comparison, see our case studies on Business Bay, Dubai Marina, Jumeirah Village Circle and Palm Jumeirah.

The next table includes all transactions, including new off-plan sales, between 1 January and 6 June 2026. New projects push averages up, so these figures should not be compared directly with the previous table.

Area, apartmentsAverage price per sq ft, AEDAverage price per sqm, AED
Downtown Dubai3,011About 32,410
Dubai Creek Harbour2,600About 27,990
Business Bay2,547About 27,420
Dubai Hills Estate2,432About 26,180
Dubai Marina2,058About 22,150
Dubai apartment average1,969About 21,190
Jumeirah Village Circle1,510About 16,250

Source: Property Monitor, via Engel & Völkers.

On this measure, Dubai Creek Harbour is about 14% cheaper than Downtown Dubai and about 32% above the city's apartment average.

Rental Yield: Among the Lowest of the Main Apartment Areas

Property Monitor data for August 2026, published by Engel & Völkers, shows an average gross yield of 5.12% for apartments in Dubai Creek Harbour. That is almost the same as Downtown Dubai and well below the city-wide apartment average of 6.66%, according to Engel & Völkers.

Area, August 2026Average gross apartment yield
Jumeirah Village Circle6.36%
Business Bay5.92%
Dubai Hills Estate5.82%
Dubai Marina5.51%
Dubai Creek Harbour5.12%
Downtown Dubai5.10%
Palm Jumeirah4.58%

Source: Property Monitor, via Engel & Völkers. Yields are gross, before service charges, vacancy and management fees.

Rents are now falling. In the third quarter, Metropolitan recorded an average of AED 124 per sq ft across all rental contracts, down 4.6% year on year, according to its quarterly report. Property Finder also listed Dubai Creek Harbour among nine of ten apartment communities where median asking rents fell between Q3 2025 and Q3 2026, according to Khaleej Times.

Tenant activity continues, however. The same Metropolitan report recorded 2,019 rental contracts in the quarter, up 17.2%. Of these, 68.4% were new contracts rather than renewals.

Worked Example: A One-Bedroom Resale Apartment

A one-bedroom apartment bought at the Q3 2026 average price of AED 1,736,320 and let at the average rent of AED 92,978 a year gives a gross yield of about 5.4%. If the rent is 10% lower, at about AED 83,700, the gross yield would be about 4.8%.

Both averages come from the Metropolitan Q3 2026 report. This is an illustration, not an area yield figure, so it differs from the 5.12% yield published by Property Monitor. Actual prices and rents vary between buildings. Net income will be lower after service charges, vacancy and management fees.

Dubai Creek Harbour Supply and Handover Track Record

New supply is the main risk in the area, as our guide to oversupply in Dubai real estate explains. Emaar's September 2025 report showed 10,582 completed units in the community and another 7,217 scheduled for handover by 2029, according to AGBI. Metropolitan currently lists Emaar projects in the area with handover dates running to 2030, according to its area page.

New sales add to future supply. In 2025, developers sold 2,052 off-plan apartments, according to Metropolitan. In the first half of 2026, 1,413 apartments were sold, up 74.7% year on year, according to the H1 report. The third quarter was weaker, with 457 sales, down 29.7%, according to the quarterly report.

There is no public figure for on-time handovers across the whole community. The best-documented example is Creek Gate, which was completed about 14 months late, as our case study shows. Cushman & Wakefield has also warned that contractor capacity and supply chain problems could affect handovers across Dubai, according to Khaleej Times.

For any off-plan purchase, check construction progress and escrow account details in DLD's Dubai REST app and use our handover tracker. Our guide to off-plan investment risks lists further checks.

What Is Still to Be Built?

The Metro Blue Line. The line will pass through Dubai Creek Harbour. The Roads and Transport Authority set a target of 30% completion by the end of 2026 and an opening on 9 September 2029, according to the Dubai Media Office. Until then, the community has no metro station.

Dubai Square. In December 2025, Emaar said construction had begun and was expected to take three years, according to the company's announcement.

Dubai Creek Tower. This is the least certain of the three. The foundations are already in place, and in January 2026 AGBI reported that DLD had previously marked the project as cancelled before Emaar revived the plan, according to the report. In September 2026, Emaar founder Mohamed Alabbar said the project would wait until the situation between Iran and the US settles, and gave no timeline for the tender, according to Khaleej Times. Our earlier Creek Tower news update covers the tender announcement that came before this statement.

For investors, the metro is the most firmly established of the three plans. There is no case for paying a premium today for a tower with no public timeline.

Liquidity: An Active Market, at a Slower Pace

Metropolitan recorded 1,756 resale apartment transactions in 2025, up 14.6%, according to its annual report. In the first half of 2026 there were 710 transactions, down 19.1%, according to the H1 report. The third quarter saw 294 transactions, down 28.1%, according to the quarterly report.

For comparison, the same data series recorded 2,464 resale apartment transactions in Downtown Dubai in 2025.

Ready properties made up 78.6% of resale transactions in the third quarter. The remaining 21.4% were resales of units still under construction, compared with 18.8% in 2025. Buyers can still be found, but investors should allow for a sale taking longer than it did in 2025.

Investment Scorecard

The scores summarise the analysis based on the data presented.

CategoryScore out of 10Basis for the score
Location9Waterfront location close to Downtown Dubai and the airport. No metro station until the Blue Line opens in 2029, and construction nearby is ongoing, so the score is not a full 10
Developer9Planning and much of the construction are carried out by Emaar, one of Dubai's longest-established developers. Creek Gate was completed about 14 months late, but it was delivered
Project concept8A planned waterfront community with a beach, marina and parks, combining homes, retail and offices. About 70% of the master plan area is not yet developed and the main attractions are not complete, so the score is not higher
Pricing5About 14% below Downtown Dubai and about 32% above the city's apartment average, according to Property Monitor for 1 January to 6 June 2026. The data includes off-plan transactions. The lower price than Downtown does not translate into a higher yield, so the score is mid-range
Rental potential5Average yield of 5.12%, close to Downtown Dubai and well below the city-wide apartment average of 6.66%. In Q3 2026, average rents fell by about 5% to 7% for one- to three-bedroom apartments
Value appreciation potential6Resale prices rose about 21% between 2023 and 2025, but fell 2.7% year on year in Q3 2026. The metro and the mall are still to come, and so are more than 7,000 homes
Liquidity71,756 resale apartment transactions in 2025, compared with 2,464 in Downtown Dubai in the same Metropolitan data series. In Q3 2026, the number of transactions fell 28.1% year on year

Dubai Creek Harbour suits long-term investors who are willing to accept a moderate yield and more years of construction in return for an Emaar waterfront property and a future metro connection. It suits those who need above-average rental income, or expect a quick profit while new supply keeps coming to market, less well.

What Matters for Israeli Investors?

  • First decide whether you want a ready or an off-plan property. A completed tower has a rental history you can check. A new project means waiting for handover, in some cases until 2030. Our comparison guide looks at both routes.
  • Check the immediate surroundings, not just the community name. Finished towers and construction sites sit side by side, and the view from your balcony may change.
  • Test a lower-rent scenario. Use our calculators, enter a rent below today's average and deduct service charges too.
  • Factor in the metro, but do not count on the tower. The Blue Line has an official opening date. Creek Tower does not.
  • Compare before you decide. Our Downtown Dubai case study and Dubai Hills Estate case study cover two more Emaar areas. You can follow the latest data in the Dubai property price index.

FAQ

Is Dubai Creek Harbour a good investment in 2026?

The analysis shows an established developer, an active resale market and yields of around 5%. Prices and rents weakened in Q3 2026, and more supply is still expected to reach the market. So the area suits long-term holding better than a search for quick profit.

What is the average price per square foot in Dubai Creek Harbour?

According to Metropolitan, the average resale apartment price in Q3 2026 was AED 2,300 per sq ft, or about AED 24,760 per sqm. Property Monitor's average for all transactions between 1 January and 6 June 2026, including off-plan purchases, was AED 2,600 per sq ft.

What rental yield can I expect?

According to Property Monitor data published by Engel & Völkers, the average gross apartment yield in Dubai Creek Harbour was 5.12% in August 2026, compared with 6.66% for Dubai apartments overall. This is a gross yield, before service charges, vacancy and management fees.

Has Dubai Creek Tower been built yet?

No. The foundations are in place, but in September 2026 Emaar's founder said the project would wait until the regional situation settles, and gave no timeline for the tender. So the tower should not be factored into the value of a property in the area.

Thinking of Buying in Creek Harbour Before the New Supply Arrives?

Our market analysis service looks at expected supply in the area, DLD transaction data and current rents, so you can judge whether the price is justified before you make an offer.